Takt Time - What is and why use it

What is Takt Time
Store and/or access information on a device
Learn more

 

Your personal data will be processed and information from your device (cookies, unique identifiers, and other device data) may be stored by, accessed by and shared with 141 TCF vendor(s) and 69 ad partner(s), or used specifically by this site.

 

Some vendors may process your personal data on the basis of legitimate interest, which you can object to by managing your options below. Look for a link at the bottom of this page or in the site menu to manage or withdraw consent in privacy and cookie settings.

Consent
Do not consent

Introduction

Lean Home
Takt time derived from the German word Taktzeit, which loosely translates to “rhythmic time” or “keeping a beat”, similar to the ticking of a metronome or the movement of a conductor’s baton. Takt time first was used as a production management tool in the German aircraft industry in the 1930s. It was the interval at which aircraft were moved ahead to the next production station. The concept was widely utilized within Toyota in the 1950s and was in widespread use throughout the Toyota supply base by the late 1960s.
Manage options

Takt Time Definition

Takt time is the pace of production that aligns production with customer demand, calculated as:

Takt Time = Time Available / Customer Demand in the period

It should be noted that the values ​​must be expressed in the same units of measurement, usually in seconds.

It is the heart beat of a lean organization. It is not a goal to be surpassed, but rather a target for which to aim: 

Takt Time

Takt time and Balanced Line

The visual presentation of Takt time is shown on the Line Balance chart.
Line Balancing is a production strategy that involves setting an intended rate of production for required components to be fabricated within a particular time frame. In addition, effective line balancing requires assuring that every line segment's production quota can be met within the time frame using the available production capacity.
Takt Time Bar Chart

Balance the workload of the operators get the following situation:

Takt Time Bar Chart

The requirements are as follows:

Flexible and Multi-skilled workforce, willing to accept changes in their day-to-day work area and processes
Flexible working processes and equipment, given the fact that a Takt Time variation can lead to increase or decrease of needed staff for the same operations.

Takt Time advantages

Using the Takt time will allow:
Takt Time Benefits

Takt Time FAQ:

Q1: How many Takt Time there is in a Company?

A: There is 1 Takt Time for each product's family.

Q2: How often Takt Time has to be calculated?

A: Each time there is a significant variation in customer demand or available time.

Q3: It is possible to change the Takt Time?

A: Just changing the available time but with related costs.

Q4: There is a Takt Time for each machine?

A: No, there is a Takt Time for each Value Stream.

Q5: There are resources to better understand Takt Time Calculation?

A: Yes! Dowload Takt Time Solved Exercises or use Takt Time Calculator On Line.